How Long Does Custom Millwork Take?
Updated 2 min read
The short answer
Most residential built-ins run two to five weeks from measure to final touch-up, with only one to three days on site. Kitchens and basement developments run longer. The three things that most commonly cause delays are countertop templating, long-lead appliances and inspection scheduling — none of which a carpenter directly controls.
Typical timelines
| Project | Total | On-site portion |
|---|---|---|
| Accent wall | 1–2 weeks | 1–2 days |
| Fireplace mantel / surround | 2–4 weeks | 1–2 days |
| Floating shelves | 2–3 weeks | Half a day |
| Living room built-ins | 2–5 weeks | 1–3 days |
| Media wall with services | 3–6 weeks | 2–4 days |
| Closet system (reach-in) | 2–4 weeks | Under a day |
| Walk-in closet | 4–8 weeks | 2–4 days |
| Mudroom | 3–5 weeks | 1–2 days |
| Kitchen cabinetry | 6–12 weeks | Several days, plus countertop gap |
| Whole-house trim | 3–6 weeks | 1–2 weeks |
| Basement development | Weeks to months | Ongoing, multi-trade |
Want this applied to your space?
We design and build custom work for Calgary homes. A free consultation is the first step.
What causes delays
- Countertop templating
- Stone cannot be templated until cabinetry is installed and levelled, then fabrication takes one to three weeks. This is the single most common surprise.
- Long-lead appliances
- Integrated units in particular. Panels are built to a specific model, so the appliance has to be confirmed before fabrication.
- Inspection scheduling
- On permitted work, inspections happen when the inspector is available, not when you are ready.
- Late design changes
- Changing a drawing costs nothing. Changing a finished component means remaking it.
- Specialty finishes
- Stained work needs sample and cure stages that painted work does not.
- What is found on site
- Particularly in older homes and basements. Sometimes the honest answer is that a wall had to be opened.
Answers
Frequently asked questions
- Why does a two-day installation take five weeks?
- Because the visible part is the smallest part. Design, drawings, material ordering, shop fabrication and finishing all happen before anything arrives at your house. That sequencing is also what makes the on-site portion short and comparatively clean.
- Can a project be rushed?
- Some stages can be compressed and some genuinely cannot — finish cure times and stone fabrication are physical constraints. A trade who promises to compress those is either subcontracting the finish or planning to cut a stage.
- What is the longest part of a kitchen?
- Usually the gap between cabinetry installation and countertop installation, which is one to three weeks with no counter and often no sink. Confirming your fabricator’s lead time before the project starts lets you plan around it.